Blackfriars Primary Substation, Salford – T12 Transformer Replacement

Project Details

About Project

The new transformer is located in the redundant T11X transformer bay on the existing concrete plinth.
Works elements include:

  • Phased scrapping of the existing T11X and T12X transformers and associated equipment
  • Core drilling for additional cable ducts
  • Excavation and disposal of contaminated limestone
  • Demolition of existing plinths
  • Construct new NER plinth and sump in the new T12 transformer compound
  • Install new palisade fence
  • Modifications to surface water drainage

All works were phased to suit electrical works

 